Bulcock Street night work to take place next week
  • Friday 25 November 2011

Before work on Stage 1B of the Bulcock Street revitalisation program can be completed in early December, three evenings of night work will need to take place.

The night work will happen on 28, 29 and 30 November from about 6pm to 1am at the intersection of Bulcock Street and Otranto Avenue.

It will include trenching and road resurfacing.

Construction workers will undertake as much of the noisy work as possible during the day to keep the night time noise to a minimum.

Sunshine Coast Council appreciates the ongoing patience of the traders and the local community while these works take place.

Traffic control will be on site throughout the evening to direct traffic.

Stage 1B of the Bulcock Street revitalisation program is on schedule to be completed before the start of the summer school holidays.